A symbolic picture has been included in this news.
Jagran correspondent, Muzaffarpur. NOC has not yet been received from the Forest Department for the removal of about eight hundred trees on Chandni Chowk-Bakhri Road. For this reason all the trees are in their original condition.
While about two months ago, a proposal was sent by the Road Construction Department to count the trees, shift them and cut and remove some trees, but till now the Forest Department has not given NOC for this. Due to this, construction work is also being hampered. Where there are no trees, soil filling work is being done.
A road is also being built from Bakhri side, but if the trees are not removed then problems will have to be faced. Executive Engineer of Road Construction Department, E. Ganesh ji has not yet received the approval from the Forest Department. Some trees have to be shifted in this.
That is, it has to be removed from the construction site and installed on government land there or somewhere else. The site is being considered for this. It is also being seen that if there is land left on the roadside, these trees will be planted there. Are in touch with Forest Department officials. There is a possibility of its approval soon.
It should be noted that the Chief Minister has a possible visit to the district. He had visited this path during Pragati Yatra last year and after this administrative approval was given in the cabinet meeting. After this the construction work was started.
Work is being done with around Rs 89 crore
This scheme is worth about Rs 89 crore. Work has been going on for six months. Work has been started from Bakhri side. जीरोमाइल चौक से आगे तक मिट्टी भरने का काम किया जा रहा है। इस पथ के सिक्स लेन हो जाने से जाम की समस्या पूरी तरह समाप्त हो जाएगी। Because this is the main route to reach Darbhanga. The traffic load on it is very high. इसे देखते हुए पथ निर्माण विभाग ने इसे सिक्स लेन में तब्दील करने का निर्णय लिया था।